Latest update from Keirnan Park!
May 21
Works continue to move ahead at the Keirnan Park Recreation Precinct, with key milestones recently achieved across the pavilion and oval areas.
Recent works include:
- Underground electrical services completed for the premium oval
- Pavilion brickwork progressing well
- Rammed earth feature walls now underway
- Social room concrete slab poured
- Ongoing drainage, irrigation and earthworks across site
As our community continues to grow, we’re continuing to invest in quality recreational spaces and facilities for residents of all ages.
Stage 1A of Keirnan Park is supported by the WA Government through the PlayOn WA initiative, helping deliver important community infrastructure projects across the State.