Keirnan Park progress report
Keirnan Park Stage 1A continues to make strong progress, with major civil and pavilion works advancing across the site.
During the latest reporting period, turf sand placement and grading continued across the sporting ovals, while earthworks progressed for the rain gardens and leach drain. Formwork and reinforcement for the irrigation tank ring beam were completed, along with further preparation for the cricket facilities and water-management infrastructure.
Construction of the pavilion also moved forward, with Stage A blockwork reaching approximately 90% completion, structural steel installation progressing in Zone B and electrical and plumbing works commencing in the Zone C kitchen area.
Over the coming weeks, works will continue across the ovals, rain gardens, drainage infrastructure and pavilion. This will include further blockwork, completion of structural steel installation, mechanical ductwork, retaining wall construction and ongoing preparation of the cricket facilities.
The Shire acknowledges the WA Government for its support of the project through the PlayOn WA initiative, helping deliver modern sporting and recreation facilities for our growing community.